Step 1
Open the casing
Joint face, dowels and bore are protected before a rotor comes out. Damage done on the way out is not a repair.
Overhaul
A screw repair is decided on the bench: the rotor pair, the journals, the timing gears, the bearing positions and the seal. That is the same strip used to train dealer service engineers. A centrifugal overhaul starts with the nameplate, the hours and the stage that is actually damaged. Silverstone quotes both from that evidence, then delivers the parts and the work in one job.
Dealer service engineers are taken through the same strip used on a repair. It is not a tour of an opened casing. The repair is the damaged face, the measured bore, the bearing that belongs on that shaft, and what has to be true before the gear case is closed.
Step 1
Joint face, dowels and bore are protected before a rotor comes out. Damage done on the way out is not a repair.
Step 2
Four lobes against six. The discharge end shows which rotor is which. They are not interchangeable, and a similar airend does not share this pair.
Step 3
Rub and impact show here first. A chipped lobe tip is recorded before anyone dresses it. That mark decides repair or replacement.
Step 4
Both rotors are laid out. Journal diameter and the fillet are measured on this pair. Clearance is not copied from a look-alike airend.
Step 5
A raised edge is dressed where the inspection calls for it. The rotor is not ground down to hide a deep rub.
Step 6
The indicator is on the bore, not on the old bearing. The seat sets the replacement. The stamp on the removed bearing does not.
Step 7
The rotor goes back in with the discharge-end fit and the bearing fit checked as it seats. It is not dropped in and hoped for.
Step 8
Timing gears, bearings still in their bores, and the empty seat are read as one set. Mesh, backlash and which bore is empty are recorded before a gear comes off.
Opening the case is not the end of the job. The repair is the gear on the right shaft, the bearing in the right bore, a clean housing, and a closed case.
Step 9
The gear is marked to the shaft it came from before it leaves the case. A timing gear put back on the wrong rotor is a failed rebuild, not a parts swap.
Step 10
On this airend the bench set included QJ220-N2-MPA, NU2220-E-XL-TVP2 and NJ219-E-XL-TVP2, plus a 110 × 135 × 19 double-lip seal. Those designations belong to this machine. They are not a kit for the next airend that looks similar.
Step 11
The discharge housing and the bearing bores are cleaned before a bearing or a rotor goes back. A new bearing in a dirty bore is not a repair.
Step 12
Covers go back on only after the gears, bearings and seal have been matched. The airend that leaves the bench is closed, not left open for the photograph.
These are the photo records we hold. Customer names are not published. OEM names identify the machine already installed. A published plant story from elsewhere is not added here as our job.
One check now sits in every rotor return: after cleaning and balancing, the vibration-probe track is checked for electrical runout. A scratched probe surface can show high shaft vibration while bearing temperature and sound are normal. That reading is not treated as a failed overhaul until the probe surface has been verified.
IHI TRX160
The machine was not holding pressure. The gearbox was opened. Bull-gear and pinion bearings were replaced. A leaking air cooler was changed for a new bundle. First- and second-stage scrolls were cleaned and recoated. Impellers were cleaned and penetrant-checked before they went back on the rotor. After restart the discharge held at 0.807 MPa.










IHI TRE60 · first major overhaul
The first major stop. Cooler tubes were descaled. Rust was removed from the end covers. Third-stage scroll cavitation was repaired. Every journal and thrust bearing was measured before a replacement was decided. The rotor came out so the impellers and seal surfaces could be seen, not inferred from a casing vibration reading.




IHI TRE100
The high-speed rotor was lifted out for dynamic balancing. Journal and thrust bearings were laid out and measured. Gas seals and oil seals were checked for the leak path that puts oil into the air, or air into the oil. Scrolls, diffusers and both coolers were cleaned before the casing went back together.




IHI TX-A
At 37,451 hours the inlet scroll had cavitation, the bull-gear bearing was replaced, and the impeller was penetrant-checked. On a later visit the same machine family was surging at 0.7 MPa. The cause was the damaged inlet scroll plus a leaking intercooler. Both were replaced. Discharge then held at 0.8 MPa.


IHI TX-Z · 84,571 hours
Journals were cleaned rather than replaced on appearance alone. Cooler chambers and scrolls were recoated. The inlet guide valve was serviced. After restart the discharge stayed at 0.629 MPa.


Cameron TA6000 · about 10 years
The casing was opened across the three stages. Impellers were stripped and cleaned. Fouled diffusers were replaced rather than left in place. The gearbox was inspected and the machine was realigned before the test run. The Ingersoll Rand plate identifies the installed machine.




Atlas Copco ZH560 coolers
Fourteen dimensions were recorded on each bundle, including tube-sheet diameter, bundle length, nozzle spacing and tube pitch. The air side and the water side were then hydro-tested at 1.5 times design pressure for 20 minutes. A pneumatic seal test followed at design pressure for 30 minutes. A drop above 0.1 bar fails that test. The ZH560 air side runs near 5.5 bar on the intercooler and 8.5 bar on the aftercooler, so the test pressures were 8.25 bar and 12.75 bar.



Screw and centrifugal requests use the same form. The machine type, hours and photos decide the scope.
Compatibility notice. OEM names identify the equipment already installed. They are not a claim of genuine OEM supply, and they are not a fitment guarantee until the nameplate, model and serial number have been matched.